# What a Battery Storage Project Needs Before Lenders Issue a Term Sheet
- URL: https://blog.financely.io/what-a-battery-storage-project-needs-before-lenders-issue-a-term-sheet/
- Published: 2026-11-10T14:08:43.000Z
- Updated: 2026-11-10T14:08:43.000Z
- Description: The documents, contracts and model inputs a battery storage project needs before banks or infrastructure lenders will issue a term sheet.
- Author: Financely Debt Advisors
- Tags: Project Finance, BESS Project Finance

Battery storage is one of the most active areas of energy project finance, and one of the most misunderstood by first-time developers. Lenders are willing to finance standalone and co-located battery energy storage systems (BESS), but they will not issue a term sheet on a site, a grid queue position and a slide deck. This guide sets out what a BESS project needs to have in place before banks or infrastructure lenders will put indicative terms on paper.

## 1\. A revenue model a lender can size

Storage earns money in several ways: capacity payments, ancillary services, energy arbitrage, and contracted tolling or offtake. Lenders size debt from the revenue they believe is durable. Broadly, contracted revenue from a creditworthy counterparty supports more debt; merchant revenue supports less and is stressed harder.

- **Tolling agreements.** A counterparty pays a fixed amount for the right to dispatch the battery. This is the most financeable structure. See [how battery tolling agreements support project finance](https://blog.financely.io/how-battery-tolling-agreements-support-project-finance/).
- **Revenue floors.** A provider guarantees a minimum revenue in exchange for a share of upside. Lenders often size to the floor.
- **Capacity contracts.** Market or utility capacity payments with a defined term.
- **Merchant revenue.** Arbitrage and ancillary services, usually supported by an independent market study and sized with conservative assumptions.

Before approaching lenders, the developer should be able to show which revenue streams are contracted, for how long, with whom, and what a downside case looks like.

## 2\. Interconnection that is real

Lenders want an executed interconnection agreement, or a clear and near-term path to one, with a realistic commercial operation date, upgrade costs and any security posted. A queue position alone is not enough. For storage, lenders also check charging and discharging limits, any curtailment arrangements and whether the project is co-located with generation.

## 3\. Site control and permits

Lease or ownership of the site for at least the debt term plus a tail, zoning and land use approvals, environmental permits, and fire safety approvals. Fire codes and local permitting for lithium-ion systems have become a real diligence item, and lenders expect the developer to have engaged with the local fire authority.

## 4\. Equipment supply, warranties and the EPC route

- A supply agreement for battery modules and the power conversion system from a supplier the lender's technical adviser accepts.
- Product and performance warranties, including capacity retention and round-trip efficiency.
- A long-term service agreement covering maintenance and performance.
- An EPC or construction management structure that allocates delay and cost risk clearly. Lenders prefer a full wrap but will look at split contracts with strong interface management.

## 5\. Degradation and augmentation

Batteries lose usable capacity over time. Contracts that require the project to deliver a fixed capacity for many years need an augmentation plan: when additional modules are added, what they cost and how they are funded. Lenders want augmentation in the model and, often, a reserve to fund it. A model that assumes the battery performs at nameplate for its whole life will be sent back.

## 6\. A bankable financial model

The model must show revenue by stream and by year, degradation and augmentation, operating costs, warranties and service costs, debt sizing to a target coverage ratio, reserve accounts, and base and downside cases. See [BESS financial modelling for project finance](https://www.financely-group.com/battery-storage-bess-financial-modelling-for-project-finance?ref=blog.financely.io) and [cash flow available for debt service in project finance](https://blog.financely.io/cash-flow-available-for-debt-service-project-finance/).

## 7\. A credible capital stack

Lenders want to know where the equity comes from and when it goes in. Where tax credits apply, the structure must show how they are monetised. In the United States, storage can qualify for the [clean electricity investment credit under section 48E](https://www.irs.gov/credits-deductions/clean-electricity-investment-credit?ref=blog.financely.io), subject to the rules, and the timing of monetisation through tax equity or transfer affects the construction funding plan. Projects with remaining development costs often need development capital before debt. See [battery storage project finance with remaining development costs](https://blog.financely.io/battery-storage-project-finance-with-remaining-development-costs/).

## 8\. Independent reports

Expect the lender to require or rely on an independent engineer, a market or revenue adviser for merchant exposure, an insurance adviser and legal due diligence. Having credible advisers engaged before the term sheet stage shortens the process and gives lenders confidence that the numbers will hold.

## What a term sheet will typically address

Once the above is in place, an indicative term sheet will set out the debt quantum and how it is sized, tenor, amortisation profile, target and minimum coverage ratios, reserve requirements such as a debt service reserve and an augmentation reserve, conditions precedent and the security package. See [how to fund a debt service reserve account](https://www.financely-group.com/howto-fund-a-debt-service-reserve-account-dsra-for-project-corporate-finance?ref=blog.financely.io).

## Readiness checklist

- Revenue strategy with contracted and merchant streams separated, and a market study for the merchant portion.
- Executed or near-final interconnection agreement.
- Site control, key permits and fire authority engagement.
- Supply, warranty and service agreements, plus the construction approach.
- Degradation and augmentation plan.
- Bankable model with downside cases.
- Equity plan and, where relevant, tax credit monetisation plan.
- Independent advisers identified.

For context on where the storage financing market stands, see the [BESS project finance market overview for 2026](https://blog.financely.io/bess-project-finance-market-overview-2026/).

## The gaps that most often delay a BESS term sheet

In practice, the same few issues stall storage financings again and again. The first is a revenue case built on optimistic merchant spreads with no independent market study behind it. The second is an interconnection position that is still subject to restudy or significant upgrade cost allocation. The third is a supply agreement with weak warranties or a supplier the lender's technical adviser is not comfortable with. The fourth is a model that ignores augmentation or treats degradation as a footnote. The fifth is an equity plan that depends on a tax credit monetisation that has not been lined up.

Each of these can be fixed, but each takes time. A developer who addresses them before approaching lenders usually receives better terms and a shorter process, because the lender's diligence confirms the case instead of rebuilding it. A developer who approaches lenders first often receives conditional interest, a long list of questions and no term sheet until the answers arrive.

## How Financely helps

Financely advises battery storage developers and sponsors on bankability, structures the debt and equity, prepares the lender package and runs the process with banks, infrastructure debt funds and private credit. Financely is an advisor and arranger and does not lend or hold funds. For the full range of energy, storage and data center work, see [energy and data center project finance advisory](https://www.financely-group.com/energy-project-finance-advisory?ref=blog.financely.io).

## Frequently Asked Questions

### Can a merchant battery storage project get project finance?

Some lenders will lend against merchant or trading revenue, but usually at lower leverage and with more conservative assumptions than for contracted revenue. Many projects combine a contracted floor or tolling element with a merchant upside.

### Is a tolling agreement better than a revenue floor for financing?

A tolling agreement gives the project fixed payments from a creditworthy counterparty, which lenders size more generously. A floor protects downside while keeping upside. The right choice depends on the market and the offtaker.

### How do lenders treat battery degradation?

They model capacity fade from the supplier warranty and the operating plan, and they look at augmentation, meaning the cost and timing of adding capacity to keep meeting contracted obligations.

### Do tax credits affect BESS debt sizing?

Where available, credits such as the US clean electricity investment credit can be monetised through tax equity or transfer, which changes the capital stack. Lenders look at eligibility and the timing of monetisation.

### Does Financely lend to battery storage projects?

No. Financely is an advisor and arranger. It prepares the project for lenders and runs the process, and banks and infrastructure lenders make the credit decisions.

## Next Step

If you are preparing a financing like this, send a short summary of the transaction, the numbers and the timetable. [Request a free estimate](https://www.financely-group.com/requestaquote?ref=blog.financely.io). If you are ready to begin work straight away, you can also [start your engagement](https://www.financely.io/start-your-engagement?ref=blog.financely.io).

*Financely acts as an advisor and arranger, not a lender, issuer or guarantor, and does not hold client funds. Financing is subject to lender appetite, due diligence, compliance approval and documentation. This article is general information, not legal, tax or accounting advice.*